Update 7/9/19 – NEW TRAFFIC PATTERN – All traffic will be shifted to the north side of the median on 7/10/19.  This shift is to allow for completion of the curb on the south side of the median.

  • ROAD CLOSURE NOTIFICATION – The south side of the Harmony Road/Club Drive intersection will be closed 7/17 & 7/18 to allow for paving operations.  This is scheduled to be a daytime closure from 7:30a – 5p.  Access to the Timnath Ranch subdivision will need to be from Latham Parkway or River Pass Road.

Please Note: The construction work east of Latham Parkway is not a Town of Timnath project.  This work is being done by the Ridge at Harmony Subdivision for the Town of Windsor.  PLEASE OBEY 15 MPH POSTED SPEED LIMIT THROUGH THE INTERSECTION and through the entire construction zone – regardless of whether workers are present or not.  The reduced speed limit is in force at all times and is for your safety as well as that of the construction workers.

Note: This is a major improvement project being performed on a section of road that experiences very heavy traffic volume – especially during peak commute times in the morning and the late afternoon.  Delays should be expected and alternate routes are advised.

Project Overview

Phase 4 of The Harmony Road improvements Project will begin in January of 2019 and is expected to be completed in August of 2019.  Improvements involve the reconstruction and widening of Harmony Road from Three Bell Parkway to Latham Parkway (AKA: LCR 1 or WCR 13).  The new road section will have 4 lanes, bike lanes, raised landscaped median, and intersection improvements at Club Drive & Latham Parkway.

The majority of the roadwork will occur in Spring & Summer of 2019, however due to required work on the Lake Canal crossing that must happen before irrigation resumes in Spring 2019, there is some work that must occur during late winter/early spring.  Traffic impact should be minimal during the winter, but delays should be expected.

Schedule

Note: Orange = Work Completed

  • Connell Resources, Inc. will begin construction on January 7, 2019.
  • January 2019
    • Tree removal between Club Drive & Latham Parkway. This removal will require one lane traffic with intermittent traffic stops of up to 15 minutes.
    • Setting of concrete barricades at the Lake Canal crossing (east of Club Drive) that will require one lane traffic & intermittent traffic stops.
    • Clearing of trees and vegetation from work area
    • Construction on extensions to the Lake Canal crossing – north & south side of Harmony Road
    • Utility relocation
    • Road embankment work & fill import along the south side of Harmony Road
  • February – March 2019
    • Continued work on Lake Canal box culverts
    • Reconfigure traffic lanes to shift traffic to north side of existing road
    • Completion of embankment on south side of Harmony
    • Removal of south portion of existing road
    • City of Greeley waterline lowering
  • April 2019 – May 2019
    • Installation of traffic signals at Harmony Road & Latham Parkway
    • Installation of curb & gutter along south side of new median & at Club Drive
    • Pave bottom lift of new lanes along south side of new road & shift traffic to the south
    • Remove remainder of existing road along north side
    • North side road embankment work
    • Install remainder of median curb and gutter
  • June 2019 – August 2019
    • Pave north lanes & remainder of south lanes
    • Install median splash block
    • Install Landscape & irrigation in medians

Contact
For questions, please contact Eric Fuhrman at 970-226-0557 or via email at efuhrman@tstinc.com.
For questions concerning construction east of Latham Pkwy., please contact Justin Marshall with GLH Construction at 970-674-0440 or the Town of Windsor at 970-674-2400

Updates will be posted at Timnath.org/Harmony