Menu 

Harmony Road Construction Project Oct. 2016 – June 2017

Note: This is a major improvement project being performed on section of road that experiences very heavy traffic volume – especially during peak commute times in the morning and the afternoon.  Delays should be expected and alternate routes are advised.

harmony-project-sliderUpdate 5-19-17:

Upcoming primary construction items:

    • Patching of asphalt between the median and pavement on the north side.
    • Paving of the south side of the road, east of Three Bell (including remainder of Three Bell intersection).
    • Construction of the splash block and landscaping of the median will be continuing.  To facilitate this construction, traffic may be split at times (east bound on south side, west bound on north side).  Please be observant of changing traffic patterns.

As construction progresses, traffic patterns will be shifting with different phases of road completion.  For the safety of the crews working in the area we encourage all motorists to observe posted speed limits and use caution in the area.

Project Overview

The Harmony Road improvements involve the reconstruction and widening of Harmony Road from approximately 0.40 miles east of Main Street (CR 5) to 400’ east of Three Bell Parkway.  The new road section will have 4 lanes, bike lanes, raised landscaped median, and intersection improvements at Three Bell Parkway.  To facilitate the intersection improvements, the box culvert for the Timnath Reservoir Outlet Canal (TROC) is being replaced and will include a pedestrian underpass for a future regional trail.  The Great Western Railroad crossing will also be rebuilt to accommodate the roadway widening.

Project Map Area

Schedule

  • Connell Resources, Inc. will begin construction on October 3, 2016.
  • Fall 2016
    • Clearing of trees and vegetation from work area – Complete
    • Utility relocation
    • Shift traffic to south side of existing TROC box (maintain 2 lanes) – Complete
    • Excavation & construction of north portion of new TROC boxes – Complete
    • Road embankment work along north side – Complete
  • Winter 2016
    • New traffic signal installation at Three Bell Parkway – Complete
    • Shift traffic to north side of new TROC boxes upon completion – Complete
    • Excavation & construction of south portion of new TROC boxes – Complete
  • Spring 2017
    • Pave and shift traffic to north side of new road section – Complete
    • Remove current road surface, construct medians and south road embankment – Underway
    • Landscape medians
  • Great Western Railway will need to rebuild the railroad crossing. This work will require a full closure of Harmony Road for 1 week.  Schedule is dependent on Great Western.  Notices will be issued prior to closure.
  • The project is anticipated to be finished by late June 2017.

Emergency  Service Impact

  • The road will remain open with two way traffic being maintained as much as possible.
  • Daytime, one-lane flagging operations will be needed for some work. The contractor (via their traffic control company) should provide notifications to emergency services when those are scheduled.
  • A full closure for approximately one week will be required at some time during the project for the railroad to rebuild their crossing. Detours during that time will utilize existing roads.

Contact

For questions, please contact Eric Fuhrman at 970-226-0557 or via email at efuhrman@tstinc.com.  Updates will be posted at Timnath.org/Harmony